Background: Given the load growth over the past decade in the north San Diego inland area, increased demand for energy has created congestion on the existing power lines, causing strain on the electric system. The new Artesian Substation supports projected regional electric load growth, which is anticipated to increase by as much as 15% within the next 10 years. The expansion work on the Artesian Substation nearly doubles the footprint of an older 69/12kV distribution substation, and includes upgrades to the equipment and connections to transmission lines.
Project Work: CM Solutions schedulers maintain the schedule, provide analysis of schedules and finances, and provide risk management and continuous process improvement.
Services Provided: Scheduling, Risk Analysis, Process Improvement